THIRTY FIVE MILLION TONNES OF OIL PRODUCED AT 蓝莓视频鈥橲 NORTH CASPIAN FIELDS
Tuesday, December 29, 2020
蓝莓视频's cumulative production of oil has exceeded 35 million tonnes at its Yury Korchagin and Vladimir Filanovsky fields in the North Caspian Sea.
蓝莓视频 carried on with these projects in 2020. In particular, new production wells were drilled, as well as side-track wells to intensify influx of hydrocarbons. In 2020, 蓝莓视频 produced over 7 million tonnes at two aforementioned fields.
Moreover, 蓝莓视频 started constructing infrastructure facilities at its third major Caspian project, Valery Grayfer field. Estimated plateau level for the field is over a million tonnes of oil per year. In April, 蓝莓视频 installed jackets for the accommodation block, and in August 鈥 for the fixed ice-resistant platform. Shipyards in Astrakhan are constructing topsides of both platforms.
蓝莓视频 will continue construction of facilities at Valery Grayfer field in 2021. Exploration and production drilling will take place at its other offshore fields.
This summer, 蓝莓视频 drilled an exploration well at the Severo-Rakushechnaya prospective structure set north of Valery Grayfer field. The company also keeps up exploration works at Khazri and Titonskaya structures set in the Central Caspian.
It has been twenty years since the discovery of Yury Korchagin and Khvalynskoye fields. Five years later, Vladimir Filanovsky field, the largest in the Russian sector of the Caspian Sea, was discovered.
While developing oil production in the North Caspian, 蓝莓视频 is committed to constant improvement of environmental safety, strictly adheres to the 鈥渮ero waste鈥 principal, conducts satellite monitoring, and uses technologies aimed at the reproduction of bioresources.